Legal Column
East-West
Performance Bond Showdown
by
It
came without warning from the West. Like two legal tectonic plates colliding
were the decisions of the courts of appeal in
The
key obligations of a bonding company under its performance bond held to be so
far reaching under recent
The
The contract in Whitby Landmark stated that Whitby Landmark, the owner, was entitled to 75 per cent of any saving realized by the contractor, Mollenhauer, over the original contract cost. The cost savings were unexpectedly significant. Mollenhauer defaulted and Whitby Landmark claimed the excess costs to finish the contract over the original contract price and the 75 per cent savings.
The bonding company argued that the bond only covered completion of the contract physically, the bricks and mortar approach, while the owner’s position was that the bonding company must complete the contract in every respect in accordance with all the contract terms both physical and otherwise.
The
Ontario Court of Appeal considered the words of the bond which stated that in
the event of the contractor’s default, to promptly complete the contract in
accordance with its terms and conditions. One term of course was the 75 per cent
savings clause, and so was born the law in
In the Saskatchewan Lac La Ronge case, the trial judge followed Whitby Landmark and stated that the owner could deduct contractual liquidated damages from the amounts otherwise payable to the contractor, therefore reducing the remaining funds on the original contract. The bonding company’s obligation extended beyond the physical completion of the work.
The Saskatchewan Court of Appeal reversed the trial judge and found the wording of the bond meant the physical completion of the contract, the bricks and mortar theory, and not all the other terms of the contract between the contractor and the owner, including liquidated damages and the cost to the owner who supervised completion of the job.
The
decision in
Leave to appeal the case to the Supreme Court of Canada was not taken by the owners in Lac La Ronge. So now the tectonic plates from the West and East push against each other at an impasse. The only way to relieve pressure, according to the legal minds, is a decision in the Supreme Court of Canada as to which court was right.
For
now, however, cases in
A first year law student read a draft of this column and commented: “Would it not be easy for the bonding companies to amend their bond wording to make it clear that they are only liable for bricks and mortar in the cost of completion?”
That solution may be too simple.
David
Bristow
Q.C., LSM, C.Arb. is a partner with Team Resolution in